Getting broadband in a new build requires four separate confirmations: the address exists in provider records, a network can serve the lot, an approved path reaches the house, and an installer can activate indoor equipment. Begin before walls and hardscape are finished, and do not treat a neighbor’s service as approval for your home.

Use the ZIP search to identify area-level candidates, then open an address-specific serviceability request with each one. Save the ticket number and written status.

Separate an address problem from a construction problem

A checkout page that cannot find the house does not prove the neighborhood lacks service. Xfinity says an address may already be wired but only need to be added to its billing system; another address may require an extension of the physical network.[1]

Use these four milestones when getting internet in a new build:

MilestoneEvidence to requestNot enough
Address recognizedProvider ticket lists the exact postal address and unit, if anyAn online map pin
Lot serviceableProvider confirms the network can reach this propertyA connected neighbor
Service path approvedBuilder and provider agree on entry point, easement and required pathwayEmpty conduit chosen without provider review
Activation bookedOrder number and installation appointment for the finished homeA sales estimate

The stages matter because street construction and a home connection are different jobs. Ting describes a main network built along the street, a later fiber drop from the street to the home after an order, and an indoor appointment to install the ONT.[2] Other providers may use different equipment or sequencing, so ask each company to describe its own handoff.

Build an address packet for providers

Ask the builder or local authority for the finalized service address. Use the same spelling, street suffix and unit information on every request. If a provider cannot locate it, ask what its address-review team accepts.

Xfinity’s current proof list includes a certificate of occupancy, metered utility bill, utility welcome statement, county-assessor record, city or county permit, or the address section of a purchase agreement.[3] It treats latitude-and-longitude map screenshots and a verifiable real-estate listing as supporting material, not enough by themselves.[3] Its list is provider-specific, but it is a useful model for the packet:

  • official address document;
  • lot or parcel number;
  • latitude and longitude of the structure;
  • builder and site-superintendent contacts;
  • closing or occupancy date;
  • photos showing the street, utility side of the home and proposed entry area;
  • ticket number and every written status update.

Do not submit a nearby address to force an order. It can put billing, installation and emergency-location records on the wrong property.

The FCC National Broadband Map can show provider-reported fixed service at an address. If the home is missing, the map accepts a Location Challenge; if the location exists but provider availability appears wrong, it accepts an Availability Challenge.[4] That can improve public data, but it does not replace an order or construction approval from the provider.

Coordinate the service path before finishes close it

Ask the builder and provider to meet on the physical plan before drywall, final grading, driveway work or landscaping removes easy routes. The provider—not a generic checklist—should specify what it will use.

Builder and provider coordination checklist

  • Where will cable or fiber enter the property and the exterior wall?
  • Is the network aerial or underground at this lot?
  • Which utility easement or right-of-way must the route follow?
  • Does the provider require conduit? If so, what material, diameter, depth, bend radius, pull string, end cap and termination does its current engineering standard require?
  • Who supplies and inspects that pathway before it is covered?
  • Where will the modem, gateway or ONT sit inside?
  • Is there power, ventilation and an Ethernet route from that point to the main router location?
  • Which rooms need builder-installed Ethernet for desks, televisions or access points?
  • Who repairs blocked conduit or a route that does not meet the provider’s standard?

Do not choose conduit dimensions from a general article. Get the serving provider’s written construction specification and give it to the builder. Keep photos and measurements before trenches or walls are closed.

For deciding whether the final appointment needs a technician, see our self-install or technician guide.

Allow time for survey, permits and network work

No national installation timeline applies to new construction. Xfinity says its detailed site survey typically takes three to 10 business days, after which construction may still require a design, local permit and crew scheduling.[1] Weather, government restrictions and other issues can delay that provider’s process.[1]

Xfinity may also require customer payment for part of a network extension and a separate installation fee, depending on the construction needed.[1] It says even a home within 300 feet of its network may need construction because the route must follow easements or rights-of-way.[1] Ask for a written scope, estimated contribution, refund terms and the event that makes the address orderable before paying.

Use this sequence:

  1. Open serviceability tickets while construction is active.
  2. Resolve the official address and provide requested documents.
  3. Get a site survey and construction decision.
  4. Obtain the provider’s pathway specification before the builder closes the route.
  5. Confirm outside network and drop work are complete.
  6. Place the service order and book indoor activation.
  7. Keep temporary internet until the new line works during normal use.

Our moving internet setup guide helps coordinate an existing account. If the permanent line will miss move-in, compare short-term choices in temporary internet when moving rather than assuming a same-day wired activation. The same-day installation guide explains why equipment pickup and a construction-ready address are different situations.

Request a new-build serviceability review

The call option is for sales and plan comparison, not an existing construction-ticket status line. Give the exact address and ask whether the provider can open a serviceability review, what documents it needs and whether network construction must finish before an order.

Frequently asked questions

Why is my new address missing from internet-provider websites?

The address may need to be added to a provider’s system, or the physical network may not reach the lot. Xfinity distinguishes those outcomes in its serviceability process.[1]

Does a connected neighbor mean my new house can get service?

No. The route may depend on network distance, utility easements, rights-of-way and construction. Ask for a site-specific decision.[1]

Should my builder install conduit for broadband?

Ask the actual provider first. If conduit is required, obtain its current written dimensions, route and inspection standard; do not rely on an unverified generic specification.

Sources

  1. Xfinity: Determine Service Availability at Your Address. Xfinity, Determine Service Availability at Your Address, accessed October 20, 2026. Provider-specific address review, survey and construction process. ↩
  2. Ting Internet: Construction. Ting Internet, Construction, accessed October 20, 2026. Example of street build, drop and indoor installation as separate stages. ↩
  3. Xfinity: Documentation Required to Prove Address Serviceability. Xfinity, Documentation Required to Prove Address Serviceability, accessed October 20, 2026. Accepted and supporting address records. ↩
  4. FCC National Broadband Map: About. Federal Communications Commission, National Broadband Map About page, accessed October 20, 2026. Provider-reported availability and challenge paths. ↩

Written with AI assistance and checked against the sources listed; our data from FCC/Census as dated. FCC data as of December 30, 2025; Census ACS 5-year 2020-2024. Editorial policy